Tunnel water ingress controlLeaks and inflow stopped in tunnels, shafts and underground structures.Crack and joint injectionLeaking cracks and joints sealed, and structural cracks bonded, in concrete and masonry.Waterproofing and polyurea liningsPU membranes and polyurea linings for decks, tanks, tunnels and water structures.

Tunnels

Pre- and post-excavation groutingWater cut off and weak ground consolidated ahead of the face; voids closed behind it.Cavity and void fillingVoids above tunnel crowns, behind linings and under slabs filled without loading the support.Tunnel rehabilitationOld and operating tunnels: seepage stopped, ground consolidated and lining repaired, under traffic.

Ground

Track and slab re-levellingSettled ballastless track and slabs lifted back to level by PU injection, on live lines.Permeation and chemical groutingWeak, loose or wet ground strengthened and sealed by resins and gels that fill it without moving it.TAM groutingStaged grouting through sleeve pipes for shafts, foundations and deep excavations.Curtain and consolidation groutingSeepage cut-offs and foundation consolidation for dams, barrages, shafts and structures.Ground investigation and monitoringERT, GPR and MASW surveys, boreholes, lab tests and instruments, before and after treatment.

Rock, slopes and mines

Rock bolting and self-drilling anchorsRock bolts, self-drilling and prestressed anchors for tunnels, portals, slopes and caverns.Slope stabilisationSoil nails, anchors, mesh, drainage and rockfall barriers for slopes above roads, railways and towns.Mine shaft and strata treatmentWater sealed in shafts and declines; weak roof and face strata consolidated with resins and bolts.
All services →Grouts and resins we make →

Railways

RailwaysSettled track, transition zones and wet tunnels on running lines.

Tunnels and metro

Tunnels and metroWater, cavities and weak ground in tunnels, shafts and metro works.

Hydropower and dams

Hydropower and damsSeepage, foundations, tunnels and slopes on hydro projects.

Mining

MiningWater in shafts and declines, and weak strata at faces and in roadways.

Water, ports and highways

Water, ports and highwaysWater tunnels and shafts, micro tunnels, pipelines, manholes and highway slopes.

Heritage and buildings

Heritage and buildingsSettlement, cracks and leaks in heritage structures and buildings in use.
All industries →Projects →

Services

Tunnel water ingress controlPre- and post-excavation groutingCavity and void fillingTunnel rehabilitationTrack and slab re-levellingPermeation and chemical groutingTAM groutingCurtain and consolidation groutingRock bolting and self-drilling anchorsSlope stabilisationCrack and joint injectionWaterproofing and polyurea liningsMine shaft and strata treatmentGround investigation and monitoring

Industries

RailwaysTunnels and metroHydropower and damsMiningWater, ports and highwaysHeritage and buildings

Sales

+91 99100 18144WhatsApp +91 99100 18144connect@geoconstech.com

Tunnels and metro

A tunnel stops when water comes in, the face will not stand, or a cavity opens above the crown. Those are the jobs we are called in for. Our crews work at the face with our own pumps and with resins we formulate for the water and the ground on that site.

From Himalayan rail tunnels to a metro shaft in Delhi and a micro tunnel beside the sea.

A leak in a tunnel isn’t only water. It is time, money and reputation draining away, and the grout has to work the first time.

We probe before we grout, choose the chemistry for the water we find, and close each job against a measured result: inflow, settlement or advance.

Industry challenges

What stops a tunnel

Water ingress

Inflow under head through fractured rock or loose ground: the largest single source of delay and cost overrun underground.

Cavities and overbreak

Voids above the crown after a collapse or overbreak, which keep loosening and carry water, and which shotcrete cannot fill economically.

Weak and shear zones

Fault gouge, clay-filled joints and running ground that will not stand long enough to be supported.

Trapped machines and old tunnels

TBMs held in saturated ground, and tunnels in service that leak through their linings and cannot be closed for repair.

Two crew members injecting resin at the rock face in USBRL tunnel T-5, with cured foam around them and water still coming through
SiteInjecting at the rock face of USBRL tunnel T-5, with water still coming through, December 2015. GCPL site photograph.
Water ingress control in a tunnelCross section of a lined tunnel in jointed rock. On the left, water from the joints leaks through the lining. On the right, holes drilled through the lining and sealed with packers carry water-reactive PU into the rock, forming a treated ring that cuts the water off. BEFOREAFTER 1234567
  1. Note 1: Water-bearing joints and fractures in the rock around the tunnel.
  2. Note 2: Leaks through cracks and construction joints in the lining.
  3. Note 3: Holes drilled through the lining into the rock, in a pattern set by the leak map.
  4. Note 4: A packer seals each hole, so the resin goes into the ground and not back into the tunnel.
  5. Note 5: Water-reactive PU (DrucHyd 2C) expands on contact with water and fills joints and voids behind the lining.
  6. Note 6: The treated ring cuts the water off before it reaches the lining.
  7. Note 7: Inflow is mapped and measured before treatment, and measured again after it.
Geo Constech
Water ingress control · Cross section
Schematic · Not to scale

Our clients and success stories

Tunnels and metro work on record

Railways · Tunnels · Katra, J&K

USBRL tunnels T-1, T-3 and T-5, Katra

Heavy water ingress in Himalayan tunnels, controlled with our resin, grout design and crews: recorded by Northern Railway at up to 2,500 litres per minute.

Client letters

Railways · Tunnels · Arpinchala, J&K

T-49B escape tunnel, Arpinchala, USBRL

Cavities in a Himalayan escape tunnel treated with low-foaming and water-reactive PU resins: one of the two largest chemical grouting jobs we have held.

Subcontract

Metro · Azadpur, New Delhi

Delhi Metro CC-04, Azadpur

Two tunnel boring machines held 30 m down in loose, saturated sand. We sealed and consolidated the ground so they could be retrieved.

Project record

Railways · Tunnels · Thane–Kalyan, Maharashtra

Parsik tunnel, Thane–Kalyan

Seepage controlled in a brick-lined railway tunnel built in 1916, on a busy main line, without stopping the trains.

Certified

Ports · Micro-tunnel · Pipavav, Gujarat

Micro-tunnel pit, Pipavav

Seawater pouring into a micro-tunnel pit through a crack, after repeated attempts to seal it had failed. Sealed up to 85 per cent by grouting.

Certified

Railways · Tunnels · Banihal, J&K

Tunnel T-77D, USBRL, Banihal

A collapse at the crown left an 8 to 10 m cavity in fractured, water-bearing rock, and the ground above began to settle.

Project record
  • Tunnel T-12, ManipurManipur · Vensar ConstructionsPU grouting in soil at the portal, shaft and adit: PuTeRA grout supplied and injected by our crew, 2026Work order, February 2026, amended July 2026. Work order
  • NFR tunnel project, ManipurManipur · HCC-CPL JVGrouting material supply, 100 t Supply
  • USBRL tunnels T-3 and T-5Jammu & Kashmir · Max Infra (I) LtdSelf-drilling anchors and other products supplied, and DrucHyd 2C grout designed and applied to control water ingress, 2016Work satisfaction certificate, July 2016. Certified