Request a site inspection

Water

Tunnel water ingress controlLeaks and inflow stopped in tunnels, shafts and underground structures.Crack and joint injectionLeaking cracks and joints sealed, and structural cracks bonded, in concrete and masonry.Waterproofing and polyurea liningsPU membranes and polyurea linings for decks, tanks, tunnels and water structures.

Tunnels

Pre- and post-excavation groutingWater cut off and weak ground consolidated ahead of the face; voids closed behind it.Cavity and void fillingVoids above tunnel crowns, behind linings and under slabs filled without loading the support.Tunnel rehabilitationOld and operating tunnels: seepage stopped, ground consolidated and lining repaired, under traffic.

Ground

Track and slab re-levellingSettled ballastless track and slabs lifted back to level by PU injection, on live lines.Permeation and chemical groutingWeak, loose or wet ground strengthened and sealed by resins and gels that fill it without moving it.TAM groutingStaged grouting through sleeve pipes for shafts, foundations and deep excavations.Curtain and consolidation groutingSeepage cut-offs and foundation consolidation for dams, barrages, shafts and structures.Ground investigation and monitoringERT, GPR and MASW surveys, boreholes, lab tests and instruments, before and after treatment.

Rock, slopes and mines

Rock bolting and self-drilling anchorsRock bolts, self-drilling and prestressed anchors for tunnels, portals, slopes and caverns.Slope stabilisationSoil nails, anchors, mesh, drainage and rockfall barriers for slopes above roads, railways and towns.Mine shaft and strata treatmentWater sealed in shafts and declines; weak roof and face strata consolidated with resins and bolts.
All services →Grouts and resins we make →

Railways

RailwaysSettled track, transition zones and wet tunnels on running lines.

Tunnels and metro

Tunnels and metroWater, cavities and weak ground in tunnels, shafts and metro works.

Hydropower and dams

Hydropower and damsSeepage, foundations, tunnels and slopes on hydro projects.

Mining

MiningWater in shafts and declines, and weak strata at faces and in roadways.

Water, ports and highways

Water, ports and highwaysWater tunnels and shafts, micro tunnels, pipelines, manholes and highway slopes.

Heritage and buildings

Heritage and buildingsSettlement, cracks and leaks in heritage structures and buildings in use.
All industries →Projects →

Services

Tunnel water ingress controlPre- and post-excavation groutingCavity and void fillingTunnel rehabilitationTrack and slab re-levellingPermeation and chemical groutingTAM groutingCurtain and consolidation groutingRock bolting and self-drilling anchorsSlope stabilisationCrack and joint injectionWaterproofing and polyurea liningsMine shaft and strata treatmentGround investigation and monitoring

Industries

RailwaysTunnels and metroHydropower and damsMiningWater, ports and highwaysHeritage and buildings

Sales

+91 99100 18144WhatsApp +91 99100 18144connect@geoconstech.com

Guide · 7 min read

Settled slab track: find the cause, then lift it back on a live line

Slab track that settles once usually settles again. Lifting the slabs fixes the levels for a season; treating the ground and the water under them fixes the track. This guide sets out the order of work we follow on running lines, with the figures from T-46 P2 at Sangaldan on the USBRL.

Why slab track settles

Ballastless track spreads train loads well for as long as the formation under it stays firm and dry. When water gets in, the fine soil under the slab softens, and every passing train pumps a little of it out at the edges and joints. The slab loses support in patches, starts to rock, and settles. Each monsoon adds to it.

The causes we find most often:

  • Water entering from the uphill side, or rising from a high water table, with no cut-off and poor drainage.
  • Soft or saturated formation, often at embankments and bridge approaches.
  • Transition zones, where the track passes from a tunnel to an embankment or onto a bridge and the stiffness under it changes sharply.
  • Voids left where fines have been washed out under traffic.

Signs that the ground, not the slab, is the problem

  • Settlement that grows after each monsoon. On T-46 P2 the level surveys showed it growing by about half in the two monsoon months of 2025.
  • Highs and lows in the profile rather than an even drop, often at slab joints and transitions.
  • Slush, standing water or fines at the slab edges after rain.
  • Speed restrictions that come back after every correction.

Step 1: survey the track and the ground first

Two surveys, done before anyone drills, decide the whole job.

  • A level survey of each rail, so the lift needed at every point is known, with the cant.
  • A geophysical survey of the ground below: MASW for stiffness, ERT for water, GPR for voids. On T-46 P2 the MASW survey showed low-stiffness zones exactly where the settlement was greatest.

Together they show where the ground is weak and why. The lift and the ground treatment are both designed from them.

Step 2: design the lift and the treatment together

The method statement sets the lift at each point, the injection holes, the order of work, the quantities, and the limits on pressure and volume. It goes to the owner for approval before any drilling. The acceptance values are agreed at the same time: the levels to be reached, and how settlement will be measured afterwards.

On a running line the design also has to fit the traffic block. On T-46 P2 that meant night blocks with about five to six effective hours, drilling beside 25 kV overhead equipment only under power blocks, and the track cleared before the first train.

Step 3: lift in small steps, one rail at a time

Polyurethane injected through holes in the slab expands beneath it and lifts it. The lift is made in short cycles, with the levels read on each rail after every cycle, so the slab reseats without cracking at the joints. On a curve each rail is lifted with its own quantities and pressures to hold the cant.

On T-46 P2 we lifted with PuTeRA Level Up, our high-density hydrophobic PU, in steps of 15 to 20 mm per cycle. The largest lift was 136 mm. Inside the tunnel the correction was 12 to 48 mm, and the design profile and cant were restored on the 635 m radius curve.

PU reacts more slowly in the cold, so its reaction time is set for the night temperature on site. On T-46 P2 the nights fell below 5°C.

Re-levelling settled slab trackLong section of three track slabs. The right slab has settled below the design level, the middle slab is being lifted with PU injected through holes in steps, and the left slab is back on level with the gap below filled with grout and the weak formation treated. SETTLED1234567
  1. Note 1: Design level of the track (green dashes).
  2. Note 2: Slab settled below level, with the formation under it softened by water.
  3. Note 3: PU injected through holes in the slab, lifting it in small, controlled steps.
  4. Note 4: Levels read on each rail after every cycle, so cant and alignment are held.
  5. Note 5: The gap under the lifted slab filled with non-shrink cementitious grout.
  6. Note 6: Weak formation grouted, so the slab does not settle again.
  7. Note 7: Slab back on the design level.
Geo Constech
Slab re-levelling · Long section
Schematic · Not to scale

Step 4: fill the gap, then treat the cause

A lifted slab rests on the PU at the injection points. The space left under it is then filled with a non-shrink cementitious grout, so the slab is carried evenly again. On T-46 P2 we used a fibre-reinforced non-shrink grout.

Then the cause. Lifting alone would not have held on T-46 P2: the next monsoon would have softened the formation again. The formation along the slab edges was permeation grouted to 1 m, and a grout curtain with self-drilling anchors to 2.5 to 3 m was placed on the hill side to cut off the water.

Where the water comes from decides where the cut-off goes. Drainage that lets water leave the formation is part of the same fix.

Step 5: prove it under traffic

The job is finished when the acceptance values are met, not when the grout is in. Levels are read again under traffic, and the ground is surveyed a second time.

On T-46 P2 the residual settlement measured after traffic resumed was 0 mm. A second MASW survey confirmed the gain in ground stiffness, the slabs showed no cracking and the rail fastenings stayed tight. KRCL certified the work satisfactory in February 2026.

136mm

Largest lift, on the most settled slab.

0mm

Residual settlement, measured after traffic resumed.

12–48mm

Correction inside the tunnel. Design profile and cant restored on the curve.

What to ask any contractor before work starts

  • Which surveys come first, and what will they tell us?
  • What is the lift per cycle, and how are levels read on each rail?
  • What are the pressure and volume limits per hole, and what happens if a hole takes more?
  • How will the cause be treated, and not only the slab?
  • What acceptance values do you propose, and how will they be measured after traffic resumes?
  • Which materials, with their data sheets and batch records?

We answer all of these in the method statement, before any commercial discussion.

Questions

Also asked

Is PU lifting only for slab track?

No. The same method lifts settled floor slabs, yard pavements and approach slabs. The order of work is the same: survey, design, lift, fill, treat the cause, prove.

What if there is a void under the slab, not soft soil?

Voids are filled first, with a grout chosen for their size and for the water in them, before any lifting. Our page on cavity and void filling explains how.

Can you supply the material only?

Geo Constech does the whole job: survey, design, material and injection by our own crews. For material on its own, Aqueon Global supplies our range.

Seeing this on your line?

Send us the levels you have, where, and the traffic window. An engineer reviews it and replies with the next step.